Caltrans will fully close the Vincent Thomas Bridge (State Route 47) at 12:01 a.m. on Saturday, November 7, and keep it closed until a targeted reopening in early March 2028. Both San Pedro Bay ports expect cargo operations to continue, and the Port of Los Angeles says just 8% of port-complex drayage truck traffic uses the bridge.
That 8% describes truck traffic, not the share of containers likely to be delayed. For importers whose drayage routes cross the bridge, the risk is that longer detours disrupt truck schedules and push container pickups past their planned dates. A box can arrive and become available on time, then sit at the terminal because its truck cannot make the pickup. If the delay extends beyond the applicable free time, demurrage charges may follow.
The Closure at a Glance
| Item | Detail | Source |
|---|---|---|
| Full closure begins | Saturday, Nov. 7, 2026, 12:01 a.m. | Caltrans |
| Targeted reopening | Early March 2028 (about 16 months) | Caltrans |
| Daily bridge traffic | About 53,000 vehicles, including an estimated 4,700 heavy-duty trucks, based on 2021 bridge inspection records | Caltrans final environmental report (2024) |
| Port-complex drayage truck traffic using the bridge | 8% | Port of Los Angeles |
| Port of Los Angeles terminals | All to remain open; no expected impact on productivity, flow or capacity | Port of Los Angeles |
| Rail cargo | No expected impact from the bridge closure | Port of Los Angeles |
| Long Beach extended gates | Additional evening and Saturday gates beginning roughly two weeks before the closure; six-week program excluding Thanksgiving week | Port of Long Beach |
The closure arrives while the gateway is handling record cargo volumes. Long Beach handled 997,177 TEU in September, its busiest month in 115 years, and CEO Noel Hacegaba said the record came without terminal congestion.
Container dwell times were already rising before the bridge closure. According to the Pacific Merchant Shipping Association, average local truck container dwell across the San Pedro Bay ports reached 3.18 days in September, up from 2.95 days in August. Rail dwell increased from 6.75 to 7.19 days. Those increases predate the November shutdown and cannot be attributed to it, but they provide a useful baseline for tracking what happens afterward.
Where the 8% Shows Up
The port-level operating outlook and the risks facing individual container pickups are different. The Port of Los Angeles expects its terminals to remain open and rail cargo to move without disruption from the bridge project. It also acknowledges that local detours may add travel time for truck drivers. Whether that extra time affects your cargo depends on the route your truck uses, its appointment schedule and the capacity your drayage provider has available.
A longer drive can reduce the number of trips a truck completes in a shift. If that causes a driver to miss a terminal appointment or postpone a pickup, the container may remain at the terminal longer. Demurrage generally becomes chargeable only after the applicable free time expires, subject to the governing tariff or contract and the circumstances affecting cargo availability. The closure announcements reviewed do not establish a blanket extension of free time.
Delays can also occur after gate-out. A truck may collect its container as scheduled but take longer to reach the warehouse or distribution center, potentially disrupting delivery appointments and equipment-return plans. Tracking only the vessel ETA or terminal release date would miss these downstream effects.
Carrier advisories have already begun warning customers. Hapag-Lloyd’s October 7 North America update identifies potential congestion and cargo movement delays, although that advisory still gives the superseded November 1 start date. Caltrans’ confirmed full-closure date is November 7. Shippers should use the latest Caltrans schedule alongside carrier and terminal notices rather than relying on any single advisory.
Port-wide dwell averages may help show whether conditions deteriorate, but they cannot identify which shipments are running short of pickup time. For exposed import containers, the more actionable measure is the gap between cargo availability and actual gate-out, checked against the last free day and the truck’s confirmed pickup appointment.
If your team will be watching availability and last free days across a large set of LA and Long Beach containers this winter, walk through how ops teams set up container-level view for delays.

Which Container Pickups Are Most Exposed?
State Route 47 links San Pedro and Long Beach to Terminal Island, connecting with the I-110 Harbor Freeway, SR 103 and I-710. The Vincent Thomas Bridge carries SR 47 across the harbor’s Main Channel. Truck movements that previously crossed that span will need alternative routes during the full closure.
The Port of Los Angeles’ 8% figure measures drayage truck traffic using the bridge. It does not mean 8% of import containers will be delayed, or that every truck serving the port complex will face the same detour. Your drayage provider should be able to identify which regular terminal-to-destination routes used the bridge. Ask for that list before November 7 and match it against containers due to become available after the closure begins.
Containers moving directly by on-dock rail are less exposed to the road diversion. The Port of Los Angeles expects no impact on rail cargo moving through the port complex. Containers requiring a truck transfer before an inland rail move still need their road routes checked.
October’s overnight closures offer an early routing test. Caltrans closed the bridge westbound, toward I-110, overnight on October 4–9 and eastbound, toward Long Beach, on October 11–16, generally from 10:45 p.m. to 6:45 a.m. The westbound detour used SR 103 and Pacific Coast Highway.
A further round of westbound overnight closures is scheduled for October 18–23, also from 10:45 p.m. to 6:45 a.m. Traffic heading toward I-110 will be diverted through SR 103 and Pacific Coast Highway. Caltrans warns that construction schedules may change because of weather or operating conditions.
These temporary closures give drayage providers an opportunity to examine actual detour times and identify routes that need adjustment. They are an imperfect predictor of the full shutdown, however: October’s closures affect one direction at night, while the November closure will block both directions continuously. Use the observations to inform dispatch planning, then reassess travel times once the full diversion begins.
What Long Beach’s Extra Gates Cover
Long Beach container terminals will offer additional evening and Saturday gates under an incentive program announced on October 15. The program is scheduled to begin in late October, approximately two weeks before the November 7 closure, and continue for six weeks, excluding Thanksgiving week. It is therefore concentrated around the transition to the full bridge shutdown and its opening weeks.
The extra shifts are intended to give truckers more opportunities to collect and move containers as traffic patterns change. The port said it would monitor their use and provide further updates as needed.
For now, the announced gate program covers only the opening weeks of a closure expected to last about 16 months. Do not assume the additional shifts will continue afterward without further announcements. Likewise, an extended gate is only useful if the relevant container can be collected and the drayage provider has a driver, chassis and suitable appointment available.
The published port announcement establishes the general program window but does not specify exact additional gate dates or hours for each terminal. Confirm the operating schedule directly with the terminal where your containers will discharge, including Thanksgiving-week arrangements and any appointment requirements.
What to Re-Check Before November 7
- Pull open LA and Long Beach import containers expected to become available on or after November 7, particularly those with narrow pickup windows.
- Ask your drayage provider which terminal-to-destination routes previously crossed the Vincent Thomas Bridge, and what alternative routes and travel times it expects to use.
- For exposed containers, compare the last free day with the planned pickup appointment and actual truck availability. Add scheduling buffer where the margin is tight, and check applicable free-time terms.
- Confirm the additional evening and Saturday gate schedule at your Long Beach terminal, whether appointments are required, and whether your trucker can staff those shifts.
- For the first two weeks after November 7, monitor availability-to-gate-out time on exposed containers. Flag missed pickup appointments and containers approaching their last free day before charges become an issue.
- For containers already gated out, check delivery appointments and equipment-return plans against the revised road journey. Longer travel times can affect schedules even when pickup occurred on time.
- Keep direct on-dock rail movements on their existing plan unless operators announce changes, while continuing to monitor rail dwell and any trucking leg associated with the shipment.
Further Reading
- Caltrans: 16-Month Closure of Vincent Thomas Bridge Now Set for November 7
- Caltrans: Vincent Thomas Bridge Deck Replacement Final Environmental Report (2024)
- Caltrans: Overnight Closures of Southbound State Route 47, October 4–9
- Caltrans: Overnight and Daytime Closures of State Route 47, October 10–16
- Caltrans: Overnight Westbound Closures, October 18–23
- Port of Los Angeles: Vincent Thomas Bridge Deck Replacement Project
- Port of Long Beach: September Cargo Record and Extended-Gate Program
- PMSA: San Pedro Bay Container Dwell Times for September 2026
- Hapag-Lloyd: Week 41 North America Operational Update
- Federal Maritime Commission: Detention and Demurrage
- JOC: LA Port Stakeholders Warming to Plan to Mitigate Impact of Bridge Project
- WorldCargo News: Long Beach Sets Monthly Record as Cargo Volumes Surge 25%
- FreightWaves: New Long Beach Record as Volume Nears 1M Containers
Information current through October 16, 2026. Closure dates and preliminary construction schedules are from Caltrans releases dated September 25 and October 1, 8 and 15, 2026. The 8% drayage traffic share and terminal and rail impact statements are from the Port of Los Angeles project page. Daily bridge traffic estimates are based on Caltrans’ 2024 Final Environmental Impact Report/Environmental Assessment, which cites 2021 bridge inspection records; these estimates are not current 2026 measurements. September cargo volume and extended-gate details come from the Port of Long Beach’s October 15 briefing and subsequent release. Container dwell figures are from PMSA’s October 15 report. Gate hours, detour routes, carrier advisories and terminal operations may change during the closure. Confirm current schedules with your terminal and drayage provider, and verify free-time terms under the applicable carrier tariff or contract.
Need help interpreting this disruption or your shipment?
For a quick question, chat with Tradlinx on WhatsApp. For a deeper discussion, book a time below.
Prefer email? Contact us directly at min.so@tradlinx.com (Americas), sondre.lyndon@tradlinx.com (Europe), or henry.jo@tradlinx.com (EMEA/Asia).




Leave a Reply